These materials are from the first phase of planning, October 2025 - September 2026.
On Oct. 1, the task force narrowed the focus to the current site and is reworking the plan. Costs and projects shown here are no longer current.
The task force has determined that replacing CES is a top priority to provide a modern learning space and to address traffic and safety challenges on Main Street and identified two potential site options.
Terry Road Site
Construct a new building near the corner of Terry Road and Ebey Road, where the existing baseball and soccer fields are located.
- This project option would be less disruptive to school operations during construction.
- Disruption to athletic fields and sports during construction of new fields may occur.
- Improved parking and vehicle access points may improve traffic flow, especially on Main Street.
- Traffic may increase on Terry Road and Ebey Road, and improvements such as sidewalks would be included the project budget.
- The school district is studying if this option may require improvements to the intersection of State Route 20 and Ebey Road.
- Includes relocating the baseball field and the addition of a practice soccer field.
Existing Site
Build a new school next to the existing CES. When ready, the students would move to the new building and the old building would be demolished.
- An additional limited-access road, location to be determined, would support bus traffic and parent pick-up/drop off queueing, to support better traffic flow on Main Street.
- All athletic fields stay in their current locations.
- Construction directly adjacent to the existing school can present disruptions to learning, access to building spaces, and traffic access for the project duration.
A voter-approved bond would be necessary to provide the amount of funding needed to replace Coupeville Elementary School regardless of location.